Friday, June 17, 2011

It's looking like a house

I haven't been out to the house since Monday - and saw major progress today.  Siding is complete on the back of the house and west side.  The walls and ceilings are almost ready for primer.  Painting and flooring next week!  Only 10 weeks left...












Monday, June 13, 2011

Drywall and siding!

They finished putting up the drywall on Friday:












Today, we stopped by and mudding/taping was well underway - and the siding had been started!




Tuesday, June 7, 2011

Insulation

Insulation is ongoing - any day now, siding, drywalling, and septic tank installation should start. 




Wednesday, June 1, 2011

Wiring...check, Plumbing...check, Roofing...check

The wiring, plumbing, and roofing are complete.  I took a few pictures today of the vast nest of wires that will be hiding behind our walls.









Our completed roof:
The framing around the ductwork in the basement:


My happy place... our new backyard: